Server Migration SOP (workflow)

DTC, INC.

Server Migration SOP

Standard Operating Procedure — Milestone Workflow & Role Assignments

Owner: Project Manager   |   Applies to: HaloPSA Server Migration project template   |   Version 1.0   |   Effective 2026-09-15

1. Purpose

Defines who owns each milestone and ticket in the Server Migration HaloPSA template, worked in order from top to bottom.

2. Roles Referenced

Role

Who / What It Covers

PM

Project Manager — owns the project review.

CSA

Client Success Advisor — owns agreement/managed-services review.

Asset Admin

Owns procurement and the procurement QA review.

Lab Resource

Owns asset provisioning and hardware recycling on this template.

Field Tech

On-site technician — equipment delivery/staging and equipment pickup.

T2 Tech Resource

Handles the next-morning follow-up after each T3 migration/upgrade.

T3 Engineer

Senior resource — current default: Zach Boogher. Owns server SOW, migration prep, migration itself, and the OS upgrade.

3. Workflow — Waterfall, Top to Bottom

Milestone 1: Procurement

1 ticket — complete before moving to the next milestone.

Ticket

Assigned To

Notes

Procure Product

Asset Admin

For ordering products associated with Server Migration

Milestone 2: Staging

2 tickets — complete before moving to the next milestone.

Ticket

Assigned To

Notes

Deliver/Stage Equipment to Client

Field Tech

Field tech drops off server, stages in office, confirms remote resources are able to connect remotely so migration can take place after hours by T3 remote resource

Provision Assets

Lab Resource

This is prep server prior to staging being scheduled.

Milestone 3: Hardware Lifecycle — Server Related

6 tickets — complete before moving to the next milestone.

Ticket

Assigned To

Notes

Server SOW

T3 Engineer

Scope of work, written before migration begins.

Server Migration Prep

T3 Engineer

Handled after staging has taken place by T3 resource who is handling the migration, typically done the night before migration happens

Server Migration

T3 Engineer

After hours, the client's office is closed (see Key Rules).

Server Migration — Remote Follow-Up

T2 Tech Resource

Next business morning.

Server OS Upgrade

T3 Engineer

After hours, the client's office is closed (see Key Rules).

Server OS Upgrade — Follow-Up

T2 Tech Resource

Next business morning.

Milestone 4: Quality Assurance

7 tickets — complete before moving to the next milestone.

Ticket

Assigned To

Notes

QA — Agreement Review

CSA

Redundant with Managed Services Review — schedule only one.

QA — Endpoint Cleanup

T3 Engineer

Same T3 resource who performed the migration.

QA — Equipment Pickup

Field Tech

Scheduled after the migration is complete.

QA — Hardware Recycling

Lab Resource

This is wipe old server and prepare for disposal of hardware

QA — Managed Services Review

CSA

Redundant with Agreement Review — schedule only one.

QA — Procurement Review

Asset Admin

Review of Procurement items prior to closing out project for invoicing

QA — Project Review

Project Manager

Review of final project and tickets for invoicing to happen.

4. Key Rules

1. Work milestones from top to bottom.

2. Server Migration and Server OS Upgrade are both performed after hours, once the client's office is closed — schedule and staff accordingly. These are done in 2 different nights to minimize possible issues

3. Agreement Review and Managed Services Review are the same check from the CSA. Schedule one ticket, not both.

4. Endpoint Cleanup goes to the same T3 engineer who ran the migration, not a general T2/T3 pool.